STEP 1
Complete the on-line questionnaire and
return to AJA Registrars or request an information pack from
your local office, which will include the questionnaire for the
required service. Complete this questionnaire and return to AJA
Registrars. We will then generate a Proposal of Cost
(Quotation) for a three-year Cycle.
STEP 2
On acceptance of the quotation, submit the
signed and dated Application (which is the final page of the
Proposal of Costs) to confirm your intent to utilise the
services of AJA Registrars. A confirmation of receipt and
invoice for the first year's fees will be posted to you by
return.
STEP 3
On receipt of a signed Application, a Lead
Auditor will be allocated to your registration. He/she will
contact you to agree a provisional schedule for your
registration, explain the registration process and answer any
questions you may have.
STEP 4
When your Procedures and Manuals and
other system documentation are complete, submit these to
your allocated AJA Registrars Lead Auditor for review against
the requirements of the standard. (Note) for some standards, it
is mandatory to carry out the review on site supported by a
limited audit to validate the effectiveness of the documentation
prior to the registration audit (EMS, ISMS, and FSMS) . This is
referred to as a Document Review or Stage 1 Audit (EMS, ISMS,
FSMS). Most potential problems can be identified during the
document review/stage 1 audit and these can be eliminated by you
prior to the formal registration/compliance audit.
STEP 5
On completion of the Document Review, the
Lead Auditor will discuss and mutually confirm the registration
audit date. This will take account of any time needed to make
any adjustments to the documented system resulting from
deficiencies identified during the document review.
STEP 6
Approximately two-week prior to the
registration audit an audit itinerary will be prepared
and sent to you by the Lead Auditor. This will provide an
outline programme for the audit, identify the audit team if more
than one auditor and identify any facilities and support, which
may be required.
STEP 7
The main registration audit will commence
with an opening meeting. During this meeting the methodology and
conduct of the audit will be explained. The itinerary will also
be confirmed and an opportunity given for any questions you may
have regarding the audit. Who attends the opening meeting is a
matter for the client but it is recommended as a minimum the key
management personnel responsible for the implementation of the
system are in attendance.
STEP 8
The registration audit will consist of
sampling of objective evidence (records) observation of working
practice and discussion with personnel at all levels of your
company's organisation. A brief outline of the progress to date
of the audit will be given at the close of each day.
STEP 9
Should the Lead Auditor decide at any time
during the audit that there is a complete breakdown of the
system against the requirements of the standard, then a meeting
will be called with senior management to advise you of the
Team's findings and agree with you a course of action. It is
worth noting however that this is a rare occurrence.
STEP 10
On completion of the main registration
audit, a closing meeting will be convened to provide an
overview of the audit and detail the audit findings and
recommendations. Deficiencies identified will be documented
within a Corrective Action Request (CAR). Where these
deficiencies are minor in nature, the CAR will be designated as
a minor. Where major deficiencies are noted then the CARs will
be designated as major. Minor CARs raised only requires a
written indication of the action to be taken to address the
deficiency before the certificate can be issued. Major CARs
require completion of the corrective action and validation by
the Lead Auditor. Whenever possible this will be done by
submission of written evidence but in certain circumstances a
return visit may be required to visually check that corrective
measures have been implemented. In addition, at this meeting you
will be advised of the surveillance routine operated by AJA
Registrars.
STEP 11
It is general policy of AJA Registrars to
produce a written report on site at the time of the main
registration audit. Should this not be possible, a written
report will be prepared within 10 working days of the
registration audit. This report will then be reviewed by the
appropriate Certification Manager on behalf of the Independent
Governing Council of AJA Registrars, whose role it is to ensure
that AJA Registrars are impartial and fair in its dealings with
its customers. The Governing Council reviews reports
retrospectively.
CERTIFICATE ISSUE
Certification issue is usually within 15 working days of
completion of the audit.
SURVEILLANCE
Quotations will be provided on the basis of
a 12 monthly or 6 monthly surveillance visit routine following
the main registration audit. The 12 monthly routine is preferred
by most of AJA Registrar clients. However the option exists for
6 monthly surveillance routines (for those who prefer more
frequent visit programmes) and a quotation can be provided
accordingly. When clients fail to effectively maintain their
management system on a 12 monthly visit programme or during the
main registration audit, there were sufficient concerns to
indicate that 6 monthly visits are desirable, then AJA
Registrars would retain the right to impose 6 monthly
surveillance visits until confidence is restored.
CODE OF PRACTICE
Additional rules and conditions in AJA's
Code of Practice (CoP). The current Code of Practice will be
issued along with your Proposal/Application. It is important
that you read this carefully.
IMPARTIALITY
AJA Registrar’s Impartiality Policy
Statement can be viewed on line by clicking on the link below: